Warehouse Development
Status
Under construction
Location
Truganina
Sector
Industrial
13 Logic Court — Slab reinforcement, Sep 2026

At a glance

m² site area
2,254
m² site coverage
1,524
Office/warehouses
2

Two office/warehouse units on a 2,254 m² site in Truganina, with 1,524 m² of building coverage — under construction now.

13 Logic Court is a two-unit warehouse development in Truganina’s industrial precinct: 1,524 m² of building coverage across a 2,254 m² site.

Each warehouse has its own two-storey office with reception and tearoom, finished in painted concrete panels and Mondoclad cladding with ruby-red vertical features. Follow the build below — from the endorsed drawings to the façade going up.

Project details

  • 01Two office/warehouse units
  • 022,254 m² site · 1,524 m² site coverage (68%)
  • 03Warehouse 1 — 841 m² total building area
  • 04Warehouse 2 — 819 m² total building area
  • 05Two-storey offices with reception and tearoom
  • 06Concrete panel with Mondoclad cladding and ruby-red vertical features
  • 07Rainwater harvesting and raingardens

The design

Town planning endorsed drawings by C.C.D. Drafting Pty Ltd

North elevation drawing
North elevationStreet frontage to Logic Court
Site and ground floor plan
Site & ground floor planTwo warehouses, offices and car park
Typical office side elevation drawing
Typical office side elevationTwo-storey office
West elevation drawing
West elevationWarehouse 2
East elevation drawing
East elevationWarehouse 1

Colours & materials

  • Natural concrete · Concrete panelMain / boundary wall
  • Light grey · Painted concrete panelMain wall
  • Dark grey · Painted concrete panelMain wall
  • White · Painted concrete panelMain wall
  • Dark grey · Mondoclad metal claddingMain wall
  • Ruby red · Mondoclad metal claddingVertical feature
  • Dark grey · ZincalumeRoller door
  • Dark grey · Glazing & framesWindows

Under construction

Shot on site, month by month — from civil works to the façade going up.

  1. 01 / 04

    August 2026

    Site works & drainage

    Panels up and office frames standing while the civil works and drainage go in out front.

  2. 02 / 04

    September 2026

    Warehouse slab pour

    Reinforcement laid and the warehouse floor slabs poured under the new roof.

  3. 03 / 04

    October 2026

    Office framing

    Light-gauge steel framing for the two-storey offices goes up inside each warehouse.

  4. 04 / 04

    November 2026

    Façade & external works

    The office façades are closed in and the site is being prepared for the car park and landscaping.

1 photos